From concept to operation in under one year
In spring 2020, Eyvi actively explored opportunities in an uncertain market. One phone call quickly turned into a clear need: Four tanks for cod, as fast as possible. The team worked through the night and delivered a 3D model the very next day. May 2020 the concept and agreements were in place. August 2020 the construction started. April 2021 the facility was completed and fully operational.
The timeline was widely considered unrealistic, but for us it became a promise we were determined to deliver on.
A true start-up effort where everyone stepped in
Being a small team with only 11 people, everyone had multiple roles. Taking responsibility was what mattered. Everone worked side by side side – installing, coordinating, solving problems and keeping progress on site.
This way of working proved decisive. Not only for completing the project, but for building trust, ownership and a strong sense of team. The Arctic Cod project laid the foundation for how Eyvi still works today, with close collaboration between disciplines and a clear expectation that everyone contributes where it matters most.